New Range and Club Room – Building Progress

Finished 10 Metre Air Range

Including reduced height firing point for Juniors or Wheelchairs

??????????????????????????????? ??????????????????????????????? ??????????????????????????????? ???????????????????????????????

Wednesday 15 April

Early Shots

15 Apr 1

15 Apr 2 15 Apr 3

Sunday 12 April

Before

After

11 Apr 1 11 Apr 2 11 Apr 4

Saturday 11 April

First target changers installed

12 Apr 2

12 Apr 1

Wednesday 12 March

One more coat of paint on the outside and painting finished

11 Mar 2 11 Mar 3

Sunday 1 March

More interior pictures

1 Mar 4 1 Mar 1 1 Mar 2 1 Mar 3

Wednesday 25 February

Range in front of the firing point ready for pellet catchersM4034S-4211 M4034S-4211

Friday 20 February

Club room floor almost laid

20 Feb 4 20 Feb 1 20 Feb 2 20 Feb 3

Wednesday 28 January

Club Room painted

M4034S-4211 M4034S-4211

Friday 23 January

100 yard firing point taking shape

M4034S-4211

M4034S-4211 M4034S-4211 M4034S-4211 M4034S-4211Painting started

M4034S-4211 M4034S-4211

Friday 9 January

Club room almost ready to paint

9 January 3 9 January 2 9 January 1

Thursday 1 January

Walls removed and kitchen installed

Monday 22 December

Work starts in the club room

22 Dec 3 22 Dec 1 22 Dec 2

Friday 19 December

Target lighting and backstop before painting [volunteers needed shortly]

The new part of the club room and loos taking shape

Friday 12 December

New Front Door and others

12 Dec 4 12 Dec 1 12 Dec 2 12 Dec 3

Friday 28 November

Start made on lighting

Walls almost finished

28 November 3

28 November 1

28 November 2

Sunday 23 November

Roof finished and being tested.  No leaks

23 November 3 23 November 2 23 November 1

23 November 4 23 November 5

Wednesday 19 November

Main Roof finished. Drain pipes to be added.

Finished totally by end of the week

19 November 19 November1jpg

Friday 14 November

Main Roof Framework finished

Both roofs ready for covering

14 November 8

14 November 5 14 November 6 14 November 7

14 November 1 14 November 2 14 November 3 14 November 4

Thursday 13 November

Two roofs under way14 Nov 3 14 Nov 1 14 Nov 2

Friday 7 November

Roof supports sited correctly

7 November 5 7 November 6 7 November 1 7 November 2 7 November 3 7 November 4

Friday 31 October

Work on the roof started

31 Oct 1 31 Oct 2 31 Oct 3 31 Oct 4

Tuesday 28 October

The roof arrives

Friday 24 October

Ready for the roof

24 Oct 5 24 Oct 1 24 Oct 2 24 Oct 3 24 Oct 4

Friday 17 October

Walls up to height.  Blocks get heavier with each course.

Free keep fit classes for volunteers

17 Oct 3 17 Oct 4 17 Oct 1 17 Oct 2

Wednesday 15 October

The walls go up

15 Oct 4 15 Oct 1 15 Oct 2 15 Oct 3

First tea break since August

15 Oct 5

Friday 3 October

Concrete complete.  New loo on 100 yard building started

3 Oct 3 3 Oct 1 3 Oct 2

Friday 26 September

Two sections of concrete to go

M4034S-4211 M4034S-4211 M4034S-4211 M4034S-4211

Wednesday 24 September

Start of the base being concreted

24 Sep 2 24 Sep 3 24 Sep 4 24 Sep 5 24 Sept 1

Friday 19 September

Building Inspector has passed Excavations, Membrane and Insulation.  Concrete booked for next week

19 Sep 4 19 Sep 1 19 Sep 2 19 Sep 3

Friday 12 September

Almost ready for concrete after 140 tons of hoggin put under the sand

12 Sep 4 12 Sep 5 12 Sep 1 12 Sep 2 12 Sep 3

Friday 5 September Blocks up to damp course

5 Sep 3 5 Sep 2 5 Sep 5 5 Sep 1 5 SDep 4

Friday 29 August Day lost to weather.  Plumbing completed

31 Aug 3 31 Aug 1 31 Aug 2

Friday 22 August.  Footings concreted blockwork ready to start

22 Aug 522 Aug 422 Aug 322 Aug 222 Aug 1

 

 Sunday 17 August.  Footings nearing completion.

17 Aug 117 Aug 3217 Aug 2

By Friday 8 August base and footings partially dug out

8 Aug 38 Aug 28 Aug 18 Aug 4

Building of the new facility started Monday 4 August 2014

4 Aug 14 Aug 3 4 Aug 2